Mighty Marysville
Coal-Fired Power Plant
511 MW

PROJECT DESCRIPTION

After 80 years of operations, the “Mighty Marysville” closed in 2011 and quickly became a local hazard/eyesore. In 2014, CDC purchased the power plant from DTE Energy and agreed to demolish the plant and indemnify the company from environmental liabilities.

With environmental remediation and demolition in final stages, this site is on track to be available for new development in 2018.

Demolition Activities:

  • Implosion of power plant (500,000 sq/ft)
  • Building & structure demolition
  • Removal of asbestos containing materials and other universal waste materials
  • Site restoration